<h3></h3><h3>1、路基施工1队:</h3><h3>(1)K30+282.5-K30+405路堑破碎</h3><h3>(2)K41+045-220路堑挖方转运及爆破钻孔</h3><h3>(3)人员机械:现场管理人员2人,炮工2人,挖机3台(2台破碎)、运输车4辆、潜孔钻一套</h3><h3>2、路面施工队:</h3><h3>(1)k8+100-k8+200级配碎石底基层铺筑施工(下午材料供应不足未施工)</h3><h3>(2)人员机械:现场管理人员3人,小工2人,双桥自卸运输车5辆,平地机、压路机、装载机各一台,洒水车一辆</h3><h3>3、路基施工3队:如下图所示</h3><h3><br></h3><h3><br></h3><h3><br></h3> <h3>k30+282.5-k30+405路堑破碎</h3><h3><br></h3> <h3>k41+045-k41+200路堑挖方转运</h3> <h3>k41+045-k41+200路堑爆破钻孔</h3> <h3>k41+045-k41+200路堑破碎</h3> <h3>k8+100-k8+200级配碎石底基层铺筑施工</h3> <h3>路基施工3队</h3>